Progress Report - Week  3  -  ending Sunday 11th February 2024

Achievements during the week

  • Steel Uprights of original structure exposed where floor support steel beams will be attached

  • Position of concrete support foundations measured and marked out

  • Club house floor lifted where required and underlying ground exposed.

  • Four,  one meter cube holes dug for foundations of upright steel beams 

  • Building Control Inspector approves foundation pits 

  • Concrete mixed on site and poured to form foundation blocks for upright steels