Progress Report - Week  15  -  ending Sunday 5th May 2024

Achievements during the week​

  • Continue fit out and commissioning of electrics, fire alarms & emergency lighting

  • Completed Installation of suspended ceiling and light panels on first floor. 

  • Install Plasterboard to complete ceilings on the first floor

  • Prepare plasterboard for painting

  • Skim plasterboard where necessary