Progress Report - Week 13 - ending Sunday 21st April 2024
Achievements during the week
-
Teabar re-opens
-
Complete preparation, sealing and painting of the ground floor
-
Continue fit out and commissioning of electrics, fire alarms & emergency lighting
-
Completed installation of side walls and work bay partitions on the first floor
-
Fire sealed the main roof steel supports to full height
-
Prepare for the installation of the suspended ceiling
-
Final Building control Inspection Visit completed