Progress Report - Week  8  -  ending Sunday 17th March 2024

Achievements during the week

  • Lift manufacturer surveyors visit site to confirm technical design decisions 

  • Lift order placed with selected supplier

  • Partition for main staircase lower level installed

  • First fit of electrical wiring and services installed in ceiling void

  • Plaster boarding of ground floor ceiling almost completed

  • Filling of screw holes to plaster board fixing completed

As the build team leader said at the end of the week - Very good week for progress, everyone has worked extremely hard to get to this stage in the project. Well done.