Progress Report - Week 17 - ending Sunday 19th May 2024
Achievements during the week
-
Continue fit out and commissioning of fire alarm systems
-
Fit all doors and fire doors
-
Decorate lift lobby and staircases
-
Prime and gloss door frame and skirting boards ready to fit
The following were not achieved as the floor paint on the first floor is slow drying.
A large fan was hired in to increase the air floor to aid drying.
The following will be completed as floor paint condition allows.
-
Apply 2nd coat of floor paint as drying time permits
-
Clear central upper floor area once 2nd coated areas harden
-
Prepare central floor area for painting - Clean, Scrap, Sand
-
Paint central area of the upper floor as drying permits