top of page

Progress Report - Week  17  -  ending Sunday 19th May 2024

Achievements during the week​

  • Continue fit out and commissioning of fire alarm systems

  • Fit all doors and fire doors

  • Decorate lift lobby and staircases

  • Prime and gloss door frame and skirting boards ready to fit

The following were not achieved as the floor paint on the first floor is slow drying.

A large fan was hired in to increase the air floor to aid drying.

The following will be completed as floor paint condition allows.

  • Apply 2nd coat of floor paint as drying time permits

  • Clear central upper floor area once 2nd coated areas harden

  • Prepare central floor area for painting - Clean, Scrap, Sand

  • Paint central area of the upper floor as drying permits

bottom of page