Progress Report - Week 10 - ending Sunday 31st March 2024
Achievements during the week
-
Completed plastering over beams and uprights boxes
-
Plaster board delivery for first floor structures lifted and stored
-
Built main staircase ready for installation
-
Install main staircase & Lift Support Beams
-
Prime ground floor ceilings ready for painting
-
Paint, Paint & Paint

Plaster Board delivery for first floor fit out

Lorry crane would damage the plaster board

Ready to lift off the first pallet

Lower staircase assembled

Upper staircase assembled

Main staircase components ready for installation

Final floor repair completed

Plastering of the beams and pillar boxing completed

Installation of light fittings started

Lighting fittings positioned

Two pallet loads of plaster board unloaded

Sheets required to complete ground floor installation stored

Remaining contents of pallets lifted to first floor

Weight distributed around the first floor


Management Nerve Centre

Stairwell Wall Framework

Plaster Board fixed

Fork lift used to lift lower staircase into position

Lower stair case installed

Upper Staircase lifted into place

Upper staircase landing in position on the intermediate platform.

Seen from the first floor where the lift entrance will be.

Seen from the top of the stairs

First user of the staircase