Week 8 - w/e 17th March 2024
Progress Report - Week 8 - ending Sunday 17th March 2024
Achievements during the week
Lift manufacturer surveyors visit site to confirm technical design decisions
Lift order placed with selected supplier
Partition for main staircase lower level installed
First fit of electrical wiring and services installed in ceiling void
Plaster boarding of ground floor ceiling almost completed
Filling of screw holes to plaster board fixing completed
As the build team leader said at the end of the week - Very good week for progress, everyone has worked extremely hard to get to this stage in the project. Well done.