Week 7 - w/e 10th March 2024
Progress Report - Week 7 - ending Sunday 10th March 2024
Achievements during the week
Partition of library area removed
Insulation and Ceiling removed from the Library area
Fifth foundation pit excavated
Building Control Inspected foundation and approved
Concrete Foundation mixed and poured
Remaining floor beams installed over the library area making provision for staircase and lift
Floor board sheets installed over library area completing installation of the upper floor deck
Areas of ground floor cleared and cleaned in preparation for plaster boarding out the ceiling