Week 5 - w/e 25th February 2024

Progress Report - Week 5 - ending Sunday 25th February 2024

Achievements during the week

Final fixing of steel uprights checked and completed
Concrete floor over foundation pads brought back up to original floor level
Insultation and floor boarding restored and finished about the support uprights
Work continues to install and fix beams across the installed steel grid
As beams are secured floor board sheeting is fitted and secured
Beams installed over the new workshop area, secured and temporary boarding laid to provide access to the loft
Loft area cleared to new floor and sorted.
The majority of stored items will be discarded as outdated and no longer required.
Loft floor lifted and removed (floor in this area will be lowered to same level as new first floor.

Contact the Leamington & Warwick Model Railway Society

If you want further information about the club, its activities, directions to the club rooms or the exhibition, please contact info@lwmrs.co.uk

The Leamington & Warwick Model Railway Society is a company limited by guarantee.

Registered in England and Wales Company No.: 04938339 Registered Charity Number: 1117232

bottom of page