Week 5 - w/e 25th February 2024
Progress Report - Week 5 - ending Sunday 25th February 2024
Achievements during the week
Final fixing of steel uprights checked and completed
Concrete floor over foundation pads brought back up to original floor level
Insultation and floor boarding restored and finished about the support uprights
Work continues to install and fix beams across the installed steel grid
As beams are secured floor board sheeting is fitted and secured
Beams installed over the new workshop area, secured and temporary boarding laid to provide access to the loft
Loft area cleared to new floor and sorted.
The majority of stored items will be discarded as outdated and no longer required.
Loft floor lifted and removed (floor in this area will be lowered to same level as new first floor.














