Week 4 - w/e 18th February 2024
Progress Report - Week 4 - ending Sunday 18th February 2024
Achievements during the week
Final levels for steel upright seating checked and adjusted as necessary
Steel Uprights of original structure drilled where required to enable floor support steel beams will be attached.
Steel beams delivered to site by supplier
Steel grid fully installed
First floor beams lifted into place and secured
First batch of floor sheeting lifted and moved into place ready to be secured