Achievements during the week
Steel Uprights of original structure exposed where floor support steel beams will be attached
Position of concrete support foundations measured and marked out
Club house floor lifted where required and underlying ground exposed.
Four, one meter cube holes dug for foundations of upright steel beams
Building Control Inspector approves foundation pits
Concrete mixed on site and poured to form foundation blocks for upright steels