Week 2 - w/e 4th February 2024
Progress Report - Week 2 - ending Sunday 4th February 2024
Achievements during the week
Lighting and fire alarm system made safe, lighting units removed and above ceiling wiring stripped
Ceiling stripped out with panels and insulation prepared for storage and reuse
Club house floor cleared of all other items.
Workshop partition framework built
Emergency exit staircase partition framework built