top of page
Week 18 - w/e 26th May 2024
Progress Report - Week 18 - ending Sunday 26th May 2024
Progress on the first floor is currently delayed as the paint on the floor remains tacky. As soon as possible items stored on the first floor will be moved to the side bays to allow the central area of the floor to be cleaned and painted. It is likely this area will take a further 2 weeks to dry before it can be brought into use.
Achievements during the week
Continue with final decorations and cleaning
Continue fit out and commissioning of fire alarm systems
Apply 2nd coat of floor paint as drying time permits
Clear central upper floor area once 2nd coated areas harden
Prepare central floor area for painting - Clean, Scrap, Sand
Paint central area of the upper floor as drying permits
bottom of page












