Week 18 - w/e 26th May 2024

Progress Report - Week 18 - ending Sunday 26th May 2024

Progress on the first floor is currently delayed as the paint on the floor remains tacky. As soon as possible items stored on the first floor will be moved to the side bays to allow the central area of the floor to be cleaned and painted. It is likely this area will take a further 2 weeks to dry before it can be brought into use.

Achievements during the week​

Continue with final decorations and cleaning
Continue fit out and commissioning of fire alarm systems
Apply 2nd coat of floor paint as drying time permits
Clear central upper floor area once 2nd coated areas harden
Prepare central floor area for painting - Clean, Scrap, Sand
Paint central area of the upper floor as drying permits

Contact the Leamington & Warwick Model Railway Society

If you want further information about the club, its activities, directions to the club rooms or the exhibition, please contact info@lwmrs.co.uk

The Leamington & Warwick Model Railway Society is a company limited by guarantee.

Registered in England and Wales Company No.: 04938339 Registered Charity Number: 1117232

bottom of page