Progress Report - Week 17 - ending Sunday 19th May 2024

Achievements during the week​

Continue fit out and commissioning of fire alarm systems
Fit all doors and fire doors
Decorate lift lobby and staircases
Prime and gloss door frame and skirting boards ready to fit
The following were not achieved as the floor paint on the first floor is slow drying.
A large fan was hired in to increase the air floor to aid drying.

The following will be completed as floor paint condition allows.
Apply 2nd coat of floor paint as drying time permits
Clear central upper floor area once 2nd coated areas harden
Prepare central floor area for painting - Clean, Scrap, Sand
Paint central area of the upper floor as drying permits

Contact the Leamington & Warwick Model Railway Society

If you want further information about the club, its activities, directions to the club rooms or the exhibition, please contact info@lwmrs.co.uk

The Leamington & Warwick Model Railway Society is a company limited by guarantee.

Registered in England and Wales Company No.: 04938339 Registered Charity Number: 1117232

bottom of page