top of page
Week 17 - w/e 19th May 2024
Progress Report - Week 17 - ending Sunday 19th May 2024
Achievements during the week
Continue fit out and commissioning of fire alarm systems
Fit all doors and fire doors
Decorate lift lobby and staircases
Prime and gloss door frame and skirting boards ready to fit
The following were not achieved as the floor paint on the first floor is slow drying.
A large fan was hired in to increase the air floor to aid drying.
The following will be completed as floor paint condition allows.
Apply 2nd coat of floor paint as drying time permits
Clear central upper floor area once 2nd coated areas harden
Prepare central floor area for painting - Clean, Scrap, Sand
Paint central area of the upper floor as drying permits
bottom of page












