Week 15 - w/e 5th May 2024
Progress Report - Week 15 - ending Sunday 5th May 2024
Achievements during the week
Continue fit out and commissioning of electrics, fire alarms & emergency lighting
Completed Installation of suspended ceiling and light panels on first floor.
Install Plasterboard to complete ceilings on the first floor
Prepare plasterboard for painting
Skim plasterboard where necessary