Week 13 - w/e 21st April 2024
Progress Report - Week 13 - ending Sunday 21st April 2024
Achievements during the week
Tea bar re-opens
Complete preparation, sealing and painting of the ground floor
Continue fit out and commissioning of electrics, fire alarms & emergency lighting
Completed installation of side walls and work bay partitions on the first floor
Fire sealed the main roof steel supports to full height
Prepare for the installation of the suspended ceiling
Final Building control Inspection Visit completed