Progress Report - Week 12 - ending Sunday 14th April 2024
Achievements during the week
Complete painting of lower floor ceilings and walls
Installing new ceilings to Workshop, Kitchen, hallway and toilets
Continue installation of ground floor lighting
Re-install and commission fire alarms & emergency lighting
Construction team start work on first floor